Goal 6

Home ] Goal 1 ] Goal 2 ] Goal 3 ] Goal 4 ] Goal 5 ] [ Goal 6 ] Goal 7 ] Resources ] Coversheet ]

 Revenue Recognition

References Keiso text Chapter 19, Larson text pages 35 and 36

Click here for a Word version of these notes

Deciding when to recognize revenue is an important decision for accountants. If revenue is recognized too early, the income statement will report net income sooner than it should and the business looks more profitable, in the short run, than it should. On the other hand, if revenue is reported too late, the net income will be lower than it should be. Financial statement users need to have accurate information in order to make good decisions.

When to recognize revenue?

Two conditions must be met:

  1. It is realizable - the amount of cash is known and there is a reasonable chance that it will be collected.
  2. It is earned - the earnings process is complete or almost complete. The company has performed what it was required to do.

 

Four types of revenue transactions:

  1. Revenue from selling products - recognized at the date of sale which usually means the date of delivery to the customer.
  2. Revenue from performing services - recognized after services have been performed.
  3. Revenue from the use of assets (such as interest revenue, rent revenue and royalties) - is recognized as time passes or as the assets are used.
  4. Revenue from sale of assets (not inventory) - recognized at the date of sale.

Practice Exercise

Special situations for long term construction contracts

Two methods:

1. Percentage of completion method

Revenue and gross profit on the contract are recognized as the construction takes place based on the percentage of completion of the project.

Percentage of completion is the preferred method because it more appropriately shows the revenue as the work is performed.

All of the following conditions must be met in order to use this method:

  1. The contract price is fixed and the costs can be estimated
  2. The buyer will be likely to fulfill the contract
  3. The seller will be likely to fulfill the contract

 

2. Completed Contract method

Revenue and gross profit are recognized only when the contract is completed. This is a more conservative method.

The completed contract method should be used when:

  1. The conditions for the percentage of completion method are not met.
  2. Contracts are short term (less than 1 year).

 

Percentage of Completion Method in detail

There are many journal entries that need to be recorded for construction projects. As the building is constructed, expenses are incurred and the customer is sent bills and is expected to make cash payments. These events need to be recorded in addition to recording revenue.

Example:

Assume the following facts for a three-year contract with a fixed price of AED 300,000.

 

1996

1997

1998

Construction costs incurred during the period

60,000

35,000

80,000

Estimated costs to complete at the end of each year

140,000

95,000

0

Billings during the year

100,000

100,000

100,000

Collections during the year

80,000

110,000

110,000

Solution:

As construction expenses are incurred, the following entry is made:

1996

Construction in progress* 60,000

                        Cash 60,000

* this is an inventory account that will remain on the balance sheet until the building is complete.

 

As bills are sent to the customer (usually based on agreements in the contract), the following entry is made:

1996

Accounts receivable 100,000

                    Billings on Contract** 100,000

**this is a liability account that will remain on the balance sheet until the building is complete. (similar to an unearned revenue account)

 

As the customer pays cash for their bills, the following entry is made:

1996

Cash 80,000

                Accounts receivable 80,000

 

Now prepare the same three entries for 1997 and 1998:

 

Recognizing revenue

In the percentage of completion method, revenue is earned on each year as the building is being built. The amount of revenue is calculated using the amount of costs incurred to estimate the percentage of completion of the building. The following journal entry is made to show the amount of revenue to be recognized:

Construction in Progress* gross profit for this period

Construction expenses** actual construction costs this period

                            Construction revenue** revenue for this period

*this account is an inventory account which appears on the balance sheet as discussed earlier.

**both construction expenses and construction revenue appear on the income statement for the current period and are closed at the end of the period.

 

The method to calculate the amounts to recognize as revenue is explained below:

Step 1

Costs are used to determine the percentage of completion of the project by using the following formula:

Costs incurred to date                         = percentage complete

Most recent estimate of total costs

 

1996

60,000/(140,000+60,000) = .3 or 30%

1997

(35,000 + 60,000)/ (95,000 + 95,000) = .5 or 50%

1998

(35,000 + 60,000 + 80,000)/ 175,000 = 1 or 100%

The building is finished in 1998.

Step 2

The total revenue to be recognized to date is calculated with the following formula:

Percentage complete * estimated total                 =                 revenue to be

                                        revenue for the contract                     recognized to date

1996

.3 * 300,000 = 90,000

1997

.5 * 300,000 = 150,000

1998

1 * 300,000 = 300,000

Step 3

To find the amounts of revenue to be recognized in the current period, the amount of revenue recognized in previous periods must be deducted.

Revenue to be          -             Revenue recognized = Current period revenue

recognized to date                 in prior periods

1996

90,000 - 0 = 90,000

1997

150,000 - 90,000 = 60,000

1998

300,000 - 90,000 - 60,000 = 150,000

Step 4

To calculate the amount of gross profit to be recorded, the costs for the current period must be subtracted from the revenues for the period.

The journal entry looks like this:

Construction in Progress gross profit for this period

Construction expenses actual construction costs this period

                            Construction revenue revenue for this period

1996

Construction in Progress 30,000

Construction expenses 60,000

                        Construction revenue 90,000

1997

Construction in Progress 25,000

Construction expenses 35,000

                        Construction revenue 60,000

1998

Construction in Progress 70,000

Construction expenses 80,000

                    Construction revenue 150,000

 

 

Income Statement Disclosure:

 

1996

1997

1998

Total

Construction revenues

90,000

60,000

150,000

300,000

Construction expenses

60,000

35,000

80,000

175,000

Gross construction profit

30,000

25,000

70,000

125,000

Notice that the billings and collections do not have any influence on the amount of revenue to be recognized.

 

Closing Entry

When the contract is completed in 1998, the two accounts relating to the contract must be closed. At the end of the contract, they will equal each other and the following entry would be made.

Billings on Contract (100,000 + 100,000 + 100,000) 300,000

                                            Construction in progress* 300,000

 

*this account would have the following activity:

Construction in Progress Account

Type of cost

Debit

Credit

1996 Construction expenses

60,000

 

1996 gross profit

30,000

 

1997 Construction expenses

35,000

 

1997 gross profit

25,000

 

1998 Construction expenses

80,000

 

1998 gross profit

70,000

 

Total

300,000

 

Closing entry

 

300,000

Final balance

0

 

Balance sheet disclosure:

 

1996

1997

1998

Current assets:

     

Accounts receivable

20,000

10,000

0

Current liabilities

     

Billings on contract

100,000

200,000

0

Less:Construction in Progress*

90,000

150,000

0

Billings in excess of costs and profits on contract

10,000

50,000

0

Important: If the billings are less than the construction in progress, then the two accounts would appear in the current asset section as inventory. The Construction in Progress account would come first and the Billings on Contract account would be deducted from it. The net amount would be called "Unbilled Contract Costs".

 

Completed Contract method

The journal entries for this method are the same as for the percentage of completion method other than the entries for recognizing revenue. Under the completed contract method, no revenue is recognized until the contract is complete.

At the end of the contract, the following entries would be made (assuming the same facts as the previous example)

To record the revenue earned and close the Billings account:

Billings on Contract 300,000

                Construction revenue 300,000

To record the construction expenses and close the construction in progress account:

Construction expenses 175,000

                Construction in progress 175,000

Note that the Construction in progress account in this method only contains the expenses and not the gross profit on the contract.

Income Statement Disclosure:

 

1996

1997

1998

Total

Construction revenues

0

0

300,000

300,000

Construction expenses

0

0

175,000

175,000

Gross construction profit

0

0

125,000

125,000

Notice that the billings and collections still do not have any influence on the amount of revenue to be recognized.

 

Balance sheet disclosure:

 

1996

1997

1998

Current assets:

     

Accounts receivable

20,000

10,000

0

Current liabilities

     

Billings on Contract

100,000

200,000

0

Less:Construction in Progress*

60,000

95,000

0

Billings in excess of costs on contract

40,000

105,000

0

Important: Again, if the billings are less than the construction in progress, then the two accounts would appear in the current asset section as inventory.

Practice questions

Home Goal 1 Goal 2 Goal 3 Goal 4 Goal 5 Goal 6 Goal 7 Resources Coversheet